一、项目基本情况
采购项目编号:JSZC-321311-XRJS-D2024-0002
采购项目名称:联恒电子10千伏供电线路迁移改造工程
二、项目终止的原因
由于前期现场勘察不到位,乙方在进场施工时发现该区域地下污水管网情况复杂,大型机械施工无法保证管网安全,不具备开挖排管作业条件,加之该段供电线路又新增用户,需增加环网柜及基础等。经过甲、乙双方多次现场会商讨论,一致认为施工方案需进一步优化完善,原施工方案实施难度大,合同无法继续履行。
三、其他补充事宜
无
四、凡对本次公告内容提出询问,请按以下方式联系
1.采购人信息
单位名称:宿迁化工科技产业园管委会(本级)
单位地址:江苏宿迁生态化工科技产业园南化路
联系人:朱怀全
联系电话:******
2.采购代理机构信息(如有)
******有限公司
单位地址:宿迁市宿城区千百美商务广场1单元1601室
联系人:张恬甜
联系电话:******
3.项目联系方式
项目联系人:张恬甜
电话:******
合同解除协议.doc","bidAttachFiles":[{"fileName":"合同解除协议.doc","fileSize":2233,"downloadUrl":"
******/fileApi/321300/fadb3efabded4c62ba7ce13176ac0d4e.doc","isNewRecord":true,"ggId":"5926e1d6f38345cb8bcad896b465f7f4","fileType":"doc"}],"cgxm":{"purchaseItemName":"其他电力系统安装","bidCallBudget":97.9,"updateDate":"2024-07-24 17:31:39","cgrXydm":"
************8W","agentAddr":"宿迁市宿城区青创魔方创业园5层509、510室","capitalCount":"0","unite":"0","projNumber":"JSZC-321311-XRJS-D2024-0002","cgysdm":"804001","proBodyName":"见资格预审文件","projContactName":"张恬甜","zoneId":"321311","ext6":"见资格预审文件","id":"febd5e
******8db19e
******d4741","ext5":"见资格预审文件","bidIndustryCode":"I","dylyId":"0","createDate":"2024-07-24 17:31:39","buyerContact":"
******","dljgXydm":"
******MA1W5MW334","bidZzxs":"2","projContactPhone":"
******","projNa
******有限公司","buyerAddr":"江苏宿迁生态化工科技产业园南化路","cgyxId":"ba526f
******668c838d
******50","isNewRecord":false,"buyerName":"宿迁化工科技产业园管委会(本级)","cgyxTitle":"宿迁化工科技产业园管委会(本级)2024年4月(第1批)政府采购意向公告","ppp":"0","agentContact":"张恬甜","purCountry":"1","purchaseItem":"B
******","capitalStandard":"见资格预审文件","hyhf":{"name":"信息传输、软件和信息技术服务业","id":"I","isNewRecord":false,"sort":30,"parentId":"0"}},"zoneId":"321311","biddedConfirmDate":"2025-02-05 00:00:00","id":"5926e1d6f38345cb8bcad896b465f7f4","ext4":"无","fileList":[{"fileName":"合同解除协议.doc","fileSize":2233,"downloadUrl":"
******/fileApi/321300/fadb3efabded4c62ba7ce13176ac0d4e.doc","isNewRecord":true,"ggId":"5926e1d6f38345cb8bcad896b465f7f4","fileType":"doc"}],"ext2":"由于前期现场勘察不到位,乙方在进场施工时发现该区域地下污水管网情况复杂,大型机械施工无法保证管网安全,不具备开挖排管作业条件,加之该段供电线路又新增用户,需增加环网柜及基础等。经过甲、乙双方多次现场会商讨论,一致认为施工方案需进一步优化完善,原施工方案实施难度大,合同无法继续履行。","createDate":"2025-02-05 10:11:24"}}